In the Task & Schedule window, the percent spent calculation has historically compared total planned time to total actual time.

Unfortunately, this approach led to confusing inconsistencies when the task list contains pruned tasks or level of effort tasks, or when the schedule has been reset to zero on a specific date.

For consistency across various views, this calculation should use direct time metrics instead.

Discussion

  • David Tuma

    David Tuma - 2012-09-17

    Fixed in Process Dashboard version 1.15

     